Construction : Tower Cranes. Assembly and decomposition of a tower crane
IHI Jib Climbing Cranes (JCC) are everyday working at Construction site. As leading supplier of JCC, IHI takes pride in the urban development.
Tower Cranes. Assembly and decomposition of a tower crane
A tower crane is indispensable to the construction of a skyscraper. Most of all the skyscrapers built in Japan until now are built by the tower crane of our company. by the way, this crane - how does it rise and go on a building? And after a building is completed, how on earth does it take down downward? We reply to the question.
Structure of a tower crane I introduce each part of a tower crane.
Generally, cranes for construction are called “Tower crane” for the shape. We named it “Jib Climbing Crane(JCC)” for it has “Jib” and climbs buildings. Let us introduce parts of tower crane to you.


How tower cranes climb
Floor-climbing
Tower crane climbs us along the number of floors constructed.

1. | Assemble a tower crane to construct several floors. |
---|

2. | The body is to be fixed on the higher floor and hydraulic cylinder pulls up the mast. |
---|

3. | The bottom of mast is to be fixed on the higher floor and then the body climbs along the mast. |
---|

4. | Tower crane repeats this process over and over just as a measuring worm. This is called “floor-climbing”. |
---|